Current Street Projects

We appreciate your patience while we work towards improving the road and infrastructure. Please contact the Transportation and Public Works Department at (817)598-4245 for any questions or for more information. You may also follow us on Facebook @weatherfordtpw for daily updates.

EAST RENTZ STREET

Beginning Wednesday, May 6, 2020, the 100-200 blocks of East Rentz Street between North Main Street and Cottonwood Drive will be closed to through traffic for pavement rehabilitation. This construction project is estimated to last approximately 2 weeks, weather permitting. Residents and businesses within the project area will have access to their property at all times. Below is a map showing alternate detour route. 

e rentz

MEADOWVIEW DRIVE

Meadowview Drive, just off of FM 730 will be widened and paved. This is in coordination with the school to help the traffic flow. For questions, call the office at (817)598-4245.

Meadowview Drive